How to check a contractor quote
By SendFair. Updated 2026-11-15.
Ask for the quote as quantities, then set them beside the calculator. A gap is not automatically padding. It is a question: which line is the extra money paying for?
Steps
Match the house
Set the calculator to the same country, floor area and number of floors.
Match the types
Pick the roof, windows, doors and tiles the quote specifies, or the closest published type.
Compare line by line
Bags of cement, tonnes of steel, blocks, sheets and trade days should be visible on both sides.
Ask about the gap
The contractor's fee, transport and anything this page leaves out will sit on top. Ask which of those the difference is.
Their fee is allowed to be extra
This page does not include the contractor's overhead. A quote that is higher by that fee can still be honest.
A quote that will not show bags or days is the one to treat carefully.